Korean Ministry of Land, Infrastructure and Transport Notice No. 2025-1574 · Official estimating norms · 1차 정오표
Earth hauling · Dump truck productivity
General works 8-2-8 · Dump trucks · Official PDF, printed p. 179–181
Hourly output per truck
| Item | Unit | Quantity or formula |
| Output Q | ㎥/hr | 60 × q × f × E ÷ cm |
| Load volume per trip q | ㎥ | T ÷ γt × L |
| Operating efficiency E | Factor | 0.9 |
| Cover fitting and removal t5 (manual / automatic) | min | 3.77 / 0.5 |
| Wheel-wash transit t6 | min | 1.5 |
Application conditions
- q is the loose load volume. T is payload capacity (t), γt is in-situ wet density (t/m³), L is the loose-to-in-situ volume ratio and f is the volume conversion factor.
- cm is the round-trip cycle in minutes, including loading, travel, unloading, waiting to load, cover handling and wheel washing. Output depends on haul distance, road, soil and loading conditions. Use the speed and operating-condition tables in the official document.
Calculate unit cost using this norm ·
View related market unit prices
Gabion retaining wall · Installation
Civil works 2-2-3 · Gabion retaining wall installation · Official PDF, printed p. 334
Per 1 m³ installed
| Item | Unit | Quantity or formula |
| Stonemason | person-days | 0.190 |
| Skilled laborer | person-days | 0.134 |
| General laborer | person-days | 0.117 |
| 0.6 m³ excavator | hr | 0.281 |
Application conditions
- Applies to wire gabion retaining walls up to 5 m high. Includes cage assembly and installation, stone filling and lid assembly.
- Price excavation and ground leveling separately. For filter mat installation, apply General works 5-2-1, Mat laying.
Calculate unit cost using this norm ·
View related market unit prices
Tower crane · Setup, dismantling and relocation for steel erection
Building works 1-2-7 · Setup, dismantling and relocation of steel erection equipment · Official PDF, printed p. 574
Specialist scaffolder labor per crane
| Item | Unit | Quantity or formula |
| Setup | person-days | 42.0 |
| Dismantling and servicing | person-days | 42.0 |
| Vertical relocation (per move) | person-days | 6.0 |
| Tool allowance | Of labor cost | 3% |
Application conditions
- Applies to fixed external tower cranes for steel erection with 8 t hoisting capacity, 50 m working radius and 32.5 m setup height.
- Price machinery costs, material transport, foundation and bracing installation/removal, and extra trades such as electricians separately. Monthly rental rates are available under Market unit prices.
Calculate unit cost using this norm ·
View related market unit prices