Construction Cost Standards

2026 Standard construction estimating norms

These three entries were checked against the official volume and first errata. The first errata covers assembly and dismantling of drilling equipment for pile driving.

Korean Ministry of Land, Infrastructure and Transport Notice No. 2025-1574 · Official estimating norms · 1차 정오표

Earth hauling · Dump truck productivity

General works 8-2-8 · Dump trucks · Official PDF, printed p. 179–181

Hourly output per truck
ItemUnitQuantity or formula
Output Q㎥/hr60 × q × f × E ÷ cm
Load volume per trip q㎥T ÷ γt × L
Operating efficiency EFactor0.9
Cover fitting and removal t5 (manual / automatic)min3.77 / 0.5
Wheel-wash transit t6min1.5

Application conditions

  • q is the loose load volume. T is payload capacity (t), γt is in-situ wet density (t/m³), L is the loose-to-in-situ volume ratio and f is the volume conversion factor.
  • cm is the round-trip cycle in minutes, including loading, travel, unloading, waiting to load, cover handling and wheel washing. Output depends on haul distance, road, soil and loading conditions. Use the speed and operating-condition tables in the official document.
Calculate unit cost using this norm · View related market unit prices

Gabion retaining wall · Installation

Civil works 2-2-3 · Gabion retaining wall installation · Official PDF, printed p. 334

Per 1 m³ installed
ItemUnitQuantity or formula
Stonemasonperson-days0.190
Skilled laborerperson-days0.134
General laborerperson-days0.117
0.6 m³ excavatorhr0.281

Application conditions

  • Applies to wire gabion retaining walls up to 5 m high. Includes cage assembly and installation, stone filling and lid assembly.
  • Price excavation and ground leveling separately. For filter mat installation, apply General works 5-2-1, Mat laying.
Calculate unit cost using this norm · View related market unit prices

Tower crane · Setup, dismantling and relocation for steel erection

Building works 1-2-7 · Setup, dismantling and relocation of steel erection equipment · Official PDF, printed p. 574

Specialist scaffolder labor per crane
ItemUnitQuantity or formula
Setupperson-days42.0
Dismantling and servicingperson-days42.0
Vertical relocation (per move)person-days6.0
Tool allowanceOf labor cost3%

Application conditions

  • Applies to fixed external tower cranes for steel erection with 8 t hoisting capacity, 50 m working radius and 32.5 m setup height.
  • Price machinery costs, material transport, foundation and bracing installation/removal, and extra trades such as electricians separately. Monthly rental rates are available under Market unit prices.
Calculate unit cost using this norm · View related market unit prices